Liddell Building, Oxford

Our Client Monard Electrical contractors engaged with Step Energy to assist with ongoing refurbishments to Liddell building, located within the grounds of the historic Cathedral Church of Christ in Oxford.

This project formed part of a wider upgrade and refurbishment involving the installation of a small PV scheme to enhance the existing decarbonisation scheme at the location. The project and its planning application was a great example of collaboration between Client, Main Contractor, Architect, M&E Consultant & supply chain.

Step Energy were appointed to install 14 x 425W roof mounted PV panels on the south facing roof, with 1x 5KW Inverter, the 5.95 kWp system is estimated to generate 5,570 kWh annually saving an estimated 997.71 KG of CO2 the equivalent of planting around 46 trees.